| ROCHDALE
CANAL
The
Rochdale in its heyday: From Cassell’s History of
England |
Our
November meeting was addressed by Brian Holden who has been connected
with the Rochdale Canal Society since its very beginning in 1974.
In fact he had worked for many years before that on the restoration
of the Peak Forest Canal but when this project was completed he
cast around for another society to join and, unlike most of his
Peak Forest Volunteers, joined the Rochdale organisation.
Progress
on restoring the canal has varied from rapid to static, especially
during disputes caused by the withdrawal of funding, first from
one source, then another. A major problem was the ownership of
the canal and the difficulty in obtaining control of it. The Waterways
Trust resolved this in July 2000 by buying the canal outright,
using Heritage Lottery Funding. From that time onwards work has
gone ahead at a great rate.
The main contractor is Balfour Beattie along with
four subsidiary contractors. This allows work to be carried out
simultaneously at many points along the canal, instead of starting
at one end and working along its course. This speeds up the work
considerably and the contractors are confident with their target
date for reopening of 1st July 2002.
A great deal of work had been done on the Yorkshire
side of the Pennines before sufficient interest was generated
on the Manchester side, and Brian restricted most of his talk
to the latter, beginning with Lock 92 at Castlefields, a familiar
site to all SCARS members who have manned our sales stall during
the annual carnivals. He lead us through the urban landscape of
Manchester, along the brick and concrete canyons normally hidden
from view, describing the problems associated with various sites
and how they were solved. Who would know now for example that
the neat little Lock Cottage beside lock 92 was until comparatively
recently roofless and derelict, the haunt of tramps and drug users.
A wealthy Society member, Jim Ramsbottom, purchased the building
and has restored it.
A number of canal arms have been re-excavated
as the northern area of Manchester is spruced up, some new bridges
installed and the few surviving old warehouses have been given
a new lease of life.
A supermarket built across the canal was a substantial
obstacle. Negotiations resulted in a court case in which the company
was offered a large sum to demolish their store and rebuild it
away from the canal. The money paid over included a sum for the
disruption to trade caused by having to close down and restart
in a new store on the site. Strangely, the new store has never
been rebuilt.

Beneath the same lock at Miles Platting
as above – a different activity following the shallowing
of the channel |
A difficulty unique to this area resulted from
protests that the canal should be filled in because of its potential
dangers to local children. The response of the local authority
was to fill in the channel, but to leave a water depth of four
inches, a “shallows”, sure that no one could come
to any harm in so little water. In this they were quite correct,
but unfortunately the local populace continued their long standing
tradition of throwing rubbish into the canal but now it didn’t
sink into the depths but remained in view, an obvious eyesore
until eventually removed.
As part of the restoration, all these shallows are being ripped
out, and
the canal restored to near its original depth. During the early
part of this work dumpers full of spoil could be seen driving
along the canal bed and even through the locks
Some
canal arms where they cross private land into the shipping holes
of surviving canal buildings are not to be restored. A long straight
stretch of the canal has been re-excavated but piled along both
banks, creating a stark life-less aspect. Another section of new
canal has a sharp bend in it as it approaches a bridge and lock.
So sharp is the bend that long vessels have great difficulty in
negotiating it. Earlier ‘restorations’ by Manpower
Services are now showing their age, with tow paths being broken
up by plant growth. All will be addressed during the coming months.
All
the locks along the canal were ‘stanked’ that is a
wall of pilings was erected across them, to maintain water levels
and many of them were ’cascaded’ to negotiate the
9 feet drop. These are now being ripped out and new lock gates
installed, made by Callis Mill, which supplied the gates for our
own New Double Lock. Diversions are being built where immovable
obstacles like roundabouts happen to be in the way. The water
authorities have re-routed Haweswater Aqueduct which crossed the
canal inches above water level, creating a sump below the canal
to maintain the water supply. Plants and animals have been removed
from the canal and until restoration is complete, after which
they will be returned to the water. Every effort is now being
directed to the completion of the work on time. SCARS wishes Brian
and the Rochdale Canal Society every success on this final stretch,
and in the future, when it is hoped that there will still be a
role for its members to play.
Peter Keen
|